Tank & Cylinder Installation
   
Tank Installation

1. 5 foot minimum between relief valve discharge and external source of ignition (air conditioner), direct vent,
or mechanical ventilation system (attic fan).

2. If the DOT cylinder is filled on-site from a bulk truck, the filling connection and vent valve must be at least
10 feet from any external source of ignition, direct vent, or mechanical ventilation system.

 

 

 

   
  LPG Capacity Water Capacity Tare  Weight Cylinder Volume Collar  Height Footring Dia. o/s DOT/ASME Specification
Cylinder Model gallons lb. lb. cu. in. inches inches  
liters kg kg liters mm mm  
100 23.6 239.0 71.0 6629 5.1 14.5 DOT-4BW240
89.3 108.4 32.2 108.7 130 368  
200 47.2 474 147.0 13147 6.6 19.0 DOT-4BW240 
178.5 215.0 66.7 215.5 168 483  
420 99.1 1000 272.0 27737 6.6 22.0 DOT-4BW240
375.1 453.6 123.4 454.6 168 559  

Dimensions and capacities are approximate and may vary slightly from pictures

   
Above Ground Cylinders
   
   
   
Underground Tanks
   
   
 





aboutpropane.htm